Delivered on time, in the right sequence
Transit mixers, boom and stationary pumps, and a dispatch team that plans the pour with you so the site never waits for concrete.
ELR transit mixer · GaulaneThe fleet
Numbers from the Ellora Group plant and machinery register, August 2026.
- Transit mixers
- 18x 6 m³
- Boom pumps
- 236 m, 42 m
- Stationary pumps
- 250 m³/hr
- Self-loading
- 24, 2.8 m³
Plan a pour
Enter the volume, the pour rate and the distance from the plant. The planner works out loads, trucks in rotation and the pour duration.
Pour planner
Cycle = loading + round trip at city speeds + unloading at the pour rate, with 6 m³ loads. A planning aid; dispatch confirms the schedule for every order.
How a delivery day runs
Just-in-time delivery, planned the day before and followed truck by truck.
- 01
Confirm the order
Grade, volume, pour rate, pump need and site access are agreed a day ahead.
- 02
Schedule the mixers
Trucks are sequenced to the pour rate so concrete arrives as the previous load finishes.
- 03
Load and dispatch
Each truck is loaded, weighed and sent with its delivery docket.
- 04
Track to site
Dispatch follows every truck; delays are communicated before they matter.
- 05
Place and return
Pump or chute placement, washout at the plant, drum ready for the next load.
Service area
Nashik and the surrounding region
Supplied from the plant at Gaulane, Nashik. The practical radius depends on the mix, the route and the pour timing. Share your site location with the enquiry and we will confirm delivery.